Lab Objective:

The focus of this lab is to understand EIGRP implementation and configuration in Cisco IOS routers. Additional technologies tested include authentication and default routing.

Lab Topology:

The lab network topology is illustrated below:

department615

 

IMPORTANT NOTE

If you are using the www.howtonetwork.net racks, please bring up the LAN interfaces connected to the routers by issuing the no shutdown command on the connected switches. If you are using a home lab with no
Switches, you can bring up the LAN interfaces using the following configurations on your routers:

interface fastethernet 0/0
 no keepalive
 loopback
 no shutdown

Alternately, you can simply connect the interfaces to a hub or switch if you have one available in your own lab. Also, if you are using the www.howtonetwork.net racks, configure R3 as the Frame Relay switch using the following configuration commands:

hostname R3-Frame-Relay-Switch
!
frame-relay switching
!
interface serial 1/0
 description ‘Connected To R1 Serial 0/1’
 encapsulation frame-relay
 no ip address
 clock rate 128000
 frame-relay intf-type dce
 frame-relay route 102 interface serial 1/1 201
 frame-relay route 104 interface serial 1/2 401
 no shutdown
!
interface serial 1/1
 description ‘Connected To R2 Serial 0/1’
 encapsulation frame-relay
 no ip address
 clock rate 128000
 frame-relay intf-type dce
 frame-relay route 201 interface serial 1/0 102
 no shutdown
!
interface serial 1/2
 description ‘Connected To R4 Serial 0/0’
 encapsulation frame-relay
 no ip address
 clock rate 128000
 frame-relay intf-type dce
 frame-relay route 401 interface serial 1/0 104
 no shutdown
!
end

 

Task 1

Configure hostnames and IP addressing on all routers as illustrated in the network topology.

Task 2

Configure EIGRP for AS 1 across the Frame Relay WAN as illustrated in the topology. Do NOT enable EIGRP for the point-to-point link between R1 and R2.

Task 3

Configure EIGRP for AS 2 over the LAN segment between R2 and R4 as illustrated in the topology. Do NOT enable EIGRP for the point-to-point link between R1 and R2.

Task 4

Advertise the 150.1.1.0/24  via EIGRP as an External EIGRP route. This route should be injected into EIGRP with a metric of 100,000 – 100 – 255 – 1 – 1500 and administrative route tag of 1111.

Additionally, advertise the 150.6.6.0/24 subnet via EIGRP 1. The route advertised by R2 should include the administrator tag 2222 and the route advertised by R4 should include the administrative tag 4444. Ensure that R1 prefers the path via R2 to reach this subnet. In the event that this path is unavailable, R1 should prefer the path via R4. In the event that the Frame Relay WAN is down, R1 should use the point-to-point link between R1 and R2. Verify your configuration using the appropriate commands.

 

Task 5

Configure EIGRP AS 2 so that the 150.6.6.0/24 subnet uses R2s Frame Relay connection to reach the 150.1.1.0/24 subnet. In the event that R2s Frame Relay connection is down, R4s Frame Relay connection should be used.

In the event that both R2 and R4 Frame Relay connections are down, then the point-to-point link between R1 and R2 should be used. You are NOT allowed to use offset lists or modify interface bandwidth values in your solution. Verify and test your configuration.